At Eden City Maheshtala, work is in full swing as South Kolkata's largest project is ready to meet its deadline. Project Head, Adil Engineer, gives an overview on what's up at Eden City!


We are pleased to report to all our customers that the construction work at your project is progressing smoothly. You are probably aware that the real estate sector in India is going through challenging times. In Kolkata, construction work at several residential projects has significantly slowed down, if not completely stopped. However, it gives us great pleasure to inform you that the work in your Eden City Maheshtala project is continuing full fledged, without being affected at all. We are determined to ensure that your project is completed without any significant loss of time.
Adil Engineer
Project Head, Eden City, Maheshtala
PILING WORKS
[ C U R R E N T S T A T U S ]
|
Out of a total of 4298 piles in the entire project, as on 11/12/08, the total no. of piles completed is 2278 nos. |
| The piling works have been completed in Blocks C1, C2, C3, C4, C5, C6, C7, C8, C10, D2, D3, D4, D5, D6, D10, E3 and E8 (17 blocks). The work is currently going on in Blocks C9, D1, E1, E2, E7 and B1 and the scheduled completion targets are respectively as follows: C9 – first week of January 09, D1 – first week of January 09, E1 – end December 08, E2 – end January 09, E7 – end January 09, and B1 – mid January 09. |
| The work is expected to commence shortly in Blocks D11, E4, A1 and A3. |
| All piling work is expected to be completed by end April 2009. |
| SUPERSTRUCTURE WORKS |
| [ C U R R E N T S T A T U S ] |
 |
 |
BLOCK C1
7th floor slab completed.
BLOCK C2
7th floor slab completed.
BLOCK C3
3rd floor slab completed.
BLOCK C4
1st floor slab completed.
BLOCK C5
6th floor slab completed.
BLOCK C6
Pile caps and plinth tie beams completed.
BLOCK C7
2nd floor slab completed. |
BLOCK C8
Excavation for pile caps completed.
BLOCK C10
1st floor slab completed.
BLOCK D3
Excavation for pile caps in progress.
BLOCK D5
Pile caps and plinth tie beams work in progress.
BLOCK D6
Pile caps and plinth tie beams work in progress.
BLOCK E8
Pile caps and plinth tie beams work in progress. |